Event time
2021-07-29 → 2026-08-25
The dated sequence of announcements, product launches, agreement signing, and market activity.
Live evidence case / SE-BESS-SODIUM-001 / v0.1
Has sodium-ion stationary storage crossed from product and production claims into a procurable, delivered, commissioned technology with public field-operating evidence?
Decision boundary
A product announcement is not a delivery. A contract is not a commissioned site. A test facility is not customer operating history. This case covers stationary BESS only.
Current evidence state
No confidence score is inferred. Manufacturer language remains attributed unless a qualifying customer, operator, regulator, or independent record establishes the next state.
TENER Sodium publicly launched.
60 GWh agreement described by both counterparties.
Capability language is manufacturer-attributed.
A planned milestone is not a completed delivery.
No qualifying public site record accepted.
No public customer-linked dataset accepted.
No qualifying duration or reliability record.
System-level, duty-cycle-specific evidence is absent.
No universal substitution claim is inferred.
Dual clock
Event time locates the claim or agreement. Knowledge time records when StructureEvidence accepted the source into this bounded case. Both remain visible.
Event time
The dated sequence of announcements, product launches, agreement signing, and market activity.
Knowledge time / v0.1
The cutoff at which the records below were assessed. Later evidence cannot silently backfill this snapshot.
Evidence timeline
Each record supports only the narrow state written below it.
Supports a public technology and industrialization plan. Does not establish stationary BESS delivery.
Supports a manufacturer product claim. Does not establish a commissioned stationary system.
Counterparty corroboration establishes the agreement. It does not establish shipment or commissioning.
Supports product existence and stated future milestones. “Field-validated” remains source-attributed without disclosed customer field data.
Supports market activity, not a named commissioned sodium-ion customer site.
No qualifying public delivery, commissioning, grid-connection, or customer operating-history record was accepted into v0.1.
Source provenance
These are primary manufacturer and counterparty disclosures. They are useful for attribution, but are not treated as independent audits.
CATL publicly launched TENER Sodium as a stationary energy-storage product.
Open manufacturer sourceCATL and HyperStrong independently published the 60 GWh cooperation agreement.
Mass-production, field-validation, safety, and performance language remains attributable to CATL until qualifying external evidence is accepted.
Open market announcementNext state transitions
Each item is a specific transition threshold, not a general request for more information.
Supply intent does not prove fulfilled delivery.
Dated, attributable shipment and customer acceptance for a sodium-ion stationary system.
A delivered system may not be operating.
Named operator, named site, system boundary, commissioning date, and grid or service status.
Commissioning does not establish durability or reliability.
Dated runtime, duty cycle, availability, degradation, incidents, and maintenance tied to a named system.
Manufacturer test claims are not customer field validation.
Independent test or operator dataset with method, boundary, and traceable system identity.
Living case protocol
Every accepted update receives an event time and knowledge time. Earlier snapshots remain retrievable. Contradictions, corrections, and superseding evidence are appended with their scope and reason.